Paving Detailed Daily Updates
Daily Update:
Friday, August 5 – State and Cambridge Streets were completed today. This completes the 2022 Milling & Paving Program. Pavement markings will be laid out and sprayed over the next few weeks.
Thursday, August 4 – Buell Street was completed today. State and Cambridge Streets will be completed tomorrow. If all goes well, the paving will be complete tomorrow.
Wednesday, August 3 – Vega and Ash Streets were completed today. The first course on Buell Street was also placed today. The top course will be placed on Buell Street tomorrow.
Tuesday, August 2 – Sexton Street was completed today. Cherry Street was also completed along with the first course on Vega and Ash Streets. Vega and Ash Streets will be completed tomorrow and the first course on Buell Street will be started.
Monday, August 1 – Due to the morning rain and issues at the asphalt plant, the top course on Sexton Street was not quite finished today. This will be completed tomorrow then Cherry, Ash and Vega Streets will be worked on.
Friday, July 29 – the top course was completed on Tremont, East Lawlor, and Bartlett. Today Columbus Blvd and Cedar Street were completed. On Monday Sexton street will be completed and the first course will be started on Cherry, Ash, and Vega.
Thursday, July 28 – The first course was placed on Tremont, East Lawlor, and Bartlett today and the top course was placed on Tremont from Allen to Lasalle. Tomorrow the top course will be completed on Tremont, East Lawlor, and Bartlett. The top course on Sexton may be worked on as well.
Wednesday, July 27 – The top course was completed on Osgood and the first course was completed on Sexton today. The first course on Tremont, East Lawlor and Bartlett will be done tomorrow and the top course on Tremont will be started.
Tuesday, July 26 – The first course was finished on Osgood today. The top course was started on Osgood and will be finished tomorrow. The first course on Sexton, Tremont, East Lawlor, and Bartlett will be worked on tomorrow as well.
Monday, July 25 - Paving was cut short today due to the rain. The first course on Osgood Ave was worked on before the rain started. For tomorrow, the first course will be completed on Osgood Ave and the top course will be started.
Friday, July 22 – The top course on Blake road was completed today. On Monday the first course will be completed on Osgood and the top course will be worked on as well.
Thursday, July 21 – Half of the top course was completed on Blake Road before the rain storm today. Blake Road should be finished tomorrow 7/22.
Wednesday, July 20 - The first course was placed on Blake Road today. The top course will be placed on Blake Road on Thursday and Friday.
Tuesday, July 19 – Eddy Glover Blvd and Biruta Street were completed today. The first course will be placed on Blake Road tomorrow 7/20.
Monday, July 18 – Paving was cut short today due to the rain. The first course was stated on Osgood Av between Farmington Av and Burritt St before the rain started. For tomorrow, the top course will be placed on Eddy Glover Blvd (eastbound between Farmington Av and McClintock St) and Biruta St.
Friday, July 15 – Eddy Glover Blvd (westbound, from Farmington Av to McClintock St) was completed today. The first course was also placed on Biruta Street today. On Monday 7/18, the top course will be placed on Eddy Glover Blvd (eastbound, from Farmington Av to McClintock St) and Biruta Street. If all goes well, the first course on Osgood Avenue will be started.
Thursday, July 14 – Eddy Glover Blvd (Carlton St to Stanley St) and Commonwealth Avenue (Farmington Av to McClintock St) were completed today. The first course was also placed on Eddy Glover Blvd (Farmington Av to McClintock St) today. Tomorrow 7/15, Eddy Glover Blvd (Farmington Av to McClintock St), Biruta St and Osgood Avenue (Burritt St to Farmington Av) will be worked on.
Wednesday, July 13 – The top course was completed on Carlton Street and Eddy Glover Blvd, westbound from Stanley St to Carlton St today. The top course will be completed on Eddy Glover Blvd, eastbound between Stanley St and Carlton St, and Commonwealth Avenue, between Farmington Av and McClintock St. The first course will course will also be started on Eddy Glover Blvd, between Farmington Av and McClintock St.
Tuesday, July 12 – The top course was completed on Francis Street, Stanley St to Carlton St, and Carlton Street, Allen St to Francis St. Tomorrow 7/13, the top course will be completed on Carlton Street and Eddy Glover Blvd, Stanley St to Carlton St.
Monday, July 11 – The top course was placed on Commonwealth Avenue, between Eddy Glover Blvd to Stanley Street today. The top course will be placed on Francis Street, between Carlton St and Stanley St tomorrow 7/12. The top course will also be placed on Carlton Street, between Allen St and Commonwealth Av tomorrow .
Friday, July 8 – MILLING: Buell Street, Cambridge St and State Street were milled today. The milling portion is now complete. PAVING: The final course on Francis Street, between Eddy Glover Blvd and Carlton St was completed today. The top course on Commonwealth Avenue, between Eddy Glover Blvd and Stanley St will be completed on Monday 7/11.
Thursday, July 7 – MILLING: Sexton Street, Columbus Blvd, Cherry Street, Ash Street and Vega Street were completed today. Buell Street, Cambridge Street and State Street will be completed tomorrow 7/8. PAVING: The first course was finished on Francis Street and Carlton Street. The top course will be placed on Francis Street tomorrow 7/8.
Wednesday, July 6 – MILLING: Tremont Street, East Lawlor Street, Bartlett Street and part of Sexton Street were milled today. Sexton Street then Columbus Blvd will be completed tomorrow 7/7. PAVING: The first course was placed on Commonwealth Avenue, between Eddy Glover Blvd and Stanley St. Francis Street, between Eddy Glover Blvd and Carlton St was also started today. Tomorrow 7/7, the first course will be placed on Francis Street and Carlton Street.
Tuesday, July 5 – MILLING: Blake Road and the norther section of Tremont St were milled today. Tremont St, East Lawlor St, Bartlett St and Sexton St will be completed tomorrow 7/6. PAVING: Ella Grasso Blvd was completed today. The first course was also completed on Eddy Glover Blvd (between Stanley St and Carlton St). Commonwealth Av and Francis St will be worked on tomorrow.
Friday, July 1 – MILLING: The western half of Blake Road was milled today. Blake Road will be completed on Tuesday 7/5. PAVING: Pendelton Road was completed and the first course was placed on Commonwealth Avenue, between Farmington Av and McClintock St. Ella Grasso Blvd will be paved on Tuesday 7/5.
Thursday, June 30 – MILLING: Osgood Avenue was milled today. Blake Road will be milled on Friday 7/1 starting of the west end and most likely continue on Tuesday 7/5. PAVING: The paving started today on Pendelton and Lyle Roads. These two roads will be completed on Friday 7/1 and Eddy Glover Blvd will be started. Please note any scrape pieces on asphalt and boards will be picked up by the City’s Public Works Department within a couple days after paving.
Wednesday, June 29 – The milling on Eddy Glover Blvd and Biruta Street were completed today. Osgood Avenue, at the east end, was also started. Osgood Avenue will be completed tomorrow 6/30.
Tuesday, June 28 – Commonwealth Avenue was completed and Eddy Glover Blvd (Farmington Ave to McClintock St) was started today. Eddy Glover Blvd and Biruta Street will be milled tomorrow 6/39.
Monday, June 27 –The remainder of Carlton Street and Francis Street were milled today. The crew go ahead and also milled Commonwealth Ave, from Stanley St to Carlton St. The remainder of Commonwealth Ave, Eddy Glover Blvd (between Farmington Ave and McClintock St) and Biruta St will be milled tomorrow 6/28.
Friday, June 24 – Eddy Glover Blvd and Carlton Street, from Eddy Glover Blvd to Roxbury Rd, were milled today. The remainder of Carlton Street and Francis Street will be milled on Monday 6/27.
Thursday, June 23 – Pendelton Road, Lyle Road and Ella Grasso Blvd were milled today. Eddy Glover Blvd and Carlton Street will be milled tomorrow.
Wednesday, June 15 – Milling is scheduled to begin on June 23. Please see Tentative Schedule.
Tuesday, May 31 – Milling is scheduled to begin the week of June 20, 2022. Please check back a few days prior for more information.