Paving Detailed Daily Updates

Daily Update:

  • Wednesday, July 30  - Royal Oak Road and Woodhaven Drive were completed today.
    This completes the 2025 Milling and Paving Program. Pavement Markings will continue to be laid out and installed over the next few weeks.

  • Tuesday, July 29 - Despite the heat, the paving contractor completed Skipper Street, Stephen Court, Ronald Road and Adele Road today. Curbing was also installed in Walnut Hill Park. Tomorrow, Woodhaven Drive and Royal Oak Road will be completed.

  • Monday, July 28 - The first course was placed on Adele Road, Woodhaven Drive and Royal Oak Road today. For tomorrow, the top course will be completed on Skipper Street, Stephen Court and Ronald Road. The top course may also get started on Adele Road.

  • Friday, July 25 - Today the top course was placed on Sidoti Drive, Howe Road, and part of Skipper Street. On Monday the first course will be placed on Adele Road, Woodhaven Drive, and Royal Oak Road. 

  • Thursday, July 24 - Today the first course was placed on Sidoti Drive, Howe Road, Skipper Street, Ronald Road, and Stephen Court. Tomorrow the too course will be place on Sidoti Drive, Howe Road, and Skipper Street.

  • Wednesday, July 23 - The top course was completed on Sunnyslope Drive, Fairway Drive, and Rosemary Lane. Tomorrow the first course will be placed on Sidoti Drive, Howe Road, Skipper Street, Ronald Road, and Stephen Court.

  • Tuesday, July 22 - The top course was completed on Hazelmere Road, Kilbourne Avenue, and Sylvan Road today. Tomorrow the top course will be completed on Sunnyslope Drive, Fairway Drive, and Rosemary Lane.

  • Monday, July 21 - The first course was completed today on Hazelmere Road, Sunnyslope Drive, Fairway Drive, and Rosemary Lane. The top course was also started on Sunnyslope Drive. Tomorrow the top course will be worked on the following streets: Sylvan Road, Hazelmere Road, and Kilbourne Avenue.

  • Friday, July 18 - The top course was completed on Hillcrest Avenue today. The first course was also placed on Kilbourne Avenue, Sylvan Road, and part of Hazelmere Road. On Monday, the first course will be completed on Hillcrest Avenue, Sunnyslope Drive, Fairway Drive, and Rosemary Lane. The top course may also be started on Rosemary Lane and Sunnyslope Drive.

  • Thursday, July 17 - The first course was completed on Hillcrest Avenue today. The top course was also completed on Hatch Street and the southern section on Hillcrest Avenue. The top course will be completed on Hillcrest Ave tomorrow then the first course will be started on Kilbourne Avenue, Hazelmere Road and Sylvan Road.

  • Wednesday, July 16 - Wilcox Street was completed then thenfirst course was placed on Hatch Street and Hillcrest Avenue. Work will continue on Hatch Street and Hillcrest Avenue tomorrow. 

  • Tuesday, July 15 - The fist course was completed on West St and Wilcox St. The top course was also completed on West St and the southern half of Wilcox St. Tomorrow, Wilcox St will be completed then the first course will be placed on Hatch St and Hillcrest Av.

  • Monday, July 14 - Gladden Street and Smalley Street were completed today. The Contractor will work on West and Wilcox Streets tomorrow. 

  • Friday, July 11 - Cliff Street was completed today. The first course was also placed on Gladden Street and Smalley Street. Gladden Street and Smalley Street will be completed on Monday.

  • Thursday, July 10 - Paving is rained out for today.  The crew will resume tomorrow on Cliff Street, Smalley Street and Gladden Street.  A revised projected schedule is posted.

  • Wednesday, July 9 - Bank Street and Chestnut Street were completed today. The first course was also placed on Cliff Street. Tomorrow, Cliff Street will be completed then the first course will be placed on Smalley Street and Gladden Street. The top course may also be placed on Gladden Street.

  • Tuesday, July 8 - Brady Avenue, Griswald Street and Parkmore Street were completed today. Tomorrow, Bank Street will be completed then Chestnut Street and Cliff Street will be worked on.

  • Monday, July 7 - The first course was placed on Brady Avenue then the top course was completed on Sunnyledge and Harding Street today. Tomorrow, Brady Avenue will be completed then Griswald Street and Parkmore Street will be completed. Bank Street might also be worked on tomorrow. 

  • Thursday, July 3 - Walnut Hill Park was completed today. The first course was also placed on Sunnyledge and Harding Street. For Monday, the top course will be placed on Sunnyledge, Harding Street and Brady Avenue.

  • Wednesday, July 2 - Paving continued in Walnut Hill Park today. For tomorrow, the park loop will be compled then the crew will start Sunnyledge, Harding Street and possibly Brady Avenue. 

  • Tuesday, July 1 - The paving crew was delayed by the rain this morning however about half of the Walnut Hill Loop was completed. Work on the Loop will continue tomorrow. 

  • Monday, June 30 - Milling was completed on Howe Road, Sidoti Drive, Adele Road, Woodhaven Drive and Royal Oak Road today. This completes the milling portion of this year's program.
    Paving began today. The first course was completed for the Walnut Hill Loop. The top course will be started on the loop tomorrow. 

  • Friday, June 27 - Ronald Road, Stephen Court, Skipper Street and half of Howe Road were milled today. Howe Road, Sidoti Dri Cc e, Adele Road, Woodhaven Drive and Royal Oak Road will be milled tomorrow. Paving will begin in Walnut Hill Park on Monday. The loop Road will be closed to motor vehicles, cyclists and walkers.

  • Thursday, June 26 - Sylvan Road, Sunnyside Drive, Fairway Drive and Rosemary Lane were milled today. Tomorrow, Ronald Road, Stephen Court, Skipper Street, Howe Road and maybe Sidoti Drive will be milled. 

  • Wednesday, June 25 - Kilbourne Avenue and Hazelmere Road were completed and most of Sylvan Road were milled today.  For tomorrow, Sylvan Road, Sunnyslope Drive, Fairway Drive and Rosemary Lane will be milled.

  • Tuesday, June 24 - Hillcrest Avenue was completed and Kilbourne Avenue was started today. For tomorrow, Kilbourne Avenue, Hazelmere Road, Sylvan Road and maybe Sunnyslope Drive will be milled.
    The paving contractor was slowed down by the heat.  Paving will now start on Monday, June 30.

  • Monday, June 23 - Wilcox Street and Hatch Street were milled today.  Hillcrest Avenue and Kilbourne Avenue will be milled tomorrow.
  • Friday, June 20 - Milling on Smalley Street, Gladden Street, West Street was completed. The south end of Wilcox Street was also started.  For Monday, Wilcox Street, Hatch Street will be milled. Hillcrest Avenue will also be started.
  • Thursday, June 19 - Chestnut St, Cliff St and half of Smalley St we milled today. For tomorrow, Smalley St will be completed then Gladden St, West St and Wilcox St will be completed. 
  • Wednesday, June 18 - The Milling Crew finished Walnut Hill Park andBack Street today.  Tomorrow, Chestnut Street, Cliff Street, Smalley Street and Gladden Street will be milled.  Due to the recent rain, the Paving Contractor got pushed back.  Paving is anticipated to start on Thursday, June 26.  A revised projected schedule was posted.
  • Tuesday, June 17 - Milling will continue on the Walnut Hill Park Loop tomorrow. Bank Street, Chestnut Street and Cliff Street will also be milled tomorrow. 
  • Monday, June 16 - the milling crew made good progress today and was able to get a little ahead of schedule. Milling was completed on Parkmore Street, Griswold Street, Brady Avenue, Harding Street and Sunnledge.  The Walnut Hill Park Loop Road will be milled tomorrow. 
  • Friday, June 13 - Milling will begin on Monday, June 16.  Parkmore Street, Griswold Street, Brady Avenue and Harding Street will be milled on Monday.