Paving Detailed Daily Updates

Daily Update:

  • Monday, June 22 - The Milling Crew finished Yew Place, Westover Road, Heather Lane, Hale Lane, and McKinley Drive today. Tomorrow, Eastwick Road, Eastwick Court, and Governor Street will be milled. Milling will also begin on Elam Street tomorrow.

  • Tuesday, June 23 - Today milling was completed on Eastwick Road, Eastwick Court, and Governor Street. Elam Street was partially milled. Tomorrow, Elam Street will be completed, along with Mason Drive, Lakeview Avenue, and Dover Road.

  • Wednesday, June 24 - Today milling was completed on Elam Street, Mason Drive, Lakeview Avenue, and partially completed on Dover Road. Tomorrow, Dover Road, Kent Road, Dorset Road, York Road, Windsor Road, and Cornwall Road will all be worked on.

  • Thursday, June 25 - Today milling was completed on Dover Road, Kent Road, York Road, Windsor Road, Dorset Road. Tomorrow Cornwall Road and South Street will be completed. Stanley Street, Stanley Court, and Konstin Place will also all be worked on.

  • Friday, June 26Today milling was completed on Cornwall Road and South Street. Stanley Street was partially milled. On Monday, South Street, Konstin Place, and Stanley Court will be milled. Ellis Street will be worked on as well. 

Due to recent rain, paving is tentatively scheduled to begin next Wednesday, July 1st. See the updated tentative schedule attached

  • Monday, June 29 - Today milling was completed on Konstin Place and Stanley Court. Stanley Street was also worked on. Tomorrow, Stanley Street and Ellis Street will be completed.

  • Tuesday, June 30 - Today milling was completed on Stanley Street and Ellis Street. This completes the milling portion of the Pavement Management Program. Tomorrow paving will begin with the first course on Yew Place, Westover Road, Heather Lane, Hale Lane, McKinley Drive, Eastwick Road, and Eastwick Court. Governor Street may be worked on as well.

  • Wednesday, July 1 - Today the first course was placed on Yew Place, Westover Road, Heather Lane, and Eastwick Court. Eastwick Road was also worked on. Tomorrow the first course will be completed on Eastwick Road and McKinley Drive. Governor Street will also be worked on.

  • Thursday, July 2 - Today the first course was placed on Eastwick Road and McKinley Drive. Governor street was also worked on. On Monday, the first course will be completed on Governor street and the top course will also be placed.

  • Monday, July 6 - Paving was cancelled today due to the rain. If weather permits, tomorrow the first course will be completed on Governor street and the top course will also be placed.

  • Tuesday, July 7 - Paving was cancelled again today due to the rain. Tomorrow the first course will be completed on Governor street and the top course will also be placed. Yew Place and Westover Road may be worked on as well.

  • Wednesday, July 8 - Today the first course was completed on Governor Street and the top course was placed on Governor Street and Yew Place. Tomorrow, the top course will be placed on Westover Road, Heather Road, and Hale Lane. Eastwick may be worked on as well.

  • Thursday, July 9 - Today the top course was completed Westover Road. Heather Lane was also worked on. Tomorrow the top course will be finished on Heather Lane as well Eastwick Court, Eastwick Road, and Hale Lane. McKinley Drive may be worked on as well. 

  • Friday, July 10 - Today the top course was completed on Heather Lane, Hale Lane, Eastwick Court and most of Eastwick Road. On Monday the top course will be finished in Eastwick Road and McKinley Drive. Elam Street will also be worked on. 

  • Monday, July 13 - Today the top course was completed on Eastwick Road and McKinley Drive. The majority of the first course was also placed on Elam Street. Tomorrow the first course and top course will be completed on Elam Street. 

  • Tuesday, July 14 - Today the first and the top courses were both completed on Elam Street. Tomorrow the first and top courses will be completed on Lakeview Avenue and Mason Drive. Dover Road will be worked on as well. 

  • Wednesday, July 15 - Today the first and top courses were completed on Lakeview Avenue and Mason Drive. The first course was placed on Dover Road as well. Tomorrow Kent Road, Windsor Road, York Road, Dorset Road, and Cornwall Road will all be worked on.

  • Thursday, July 16 - Today the first course was completed on Kent Road, Windsor Road, York Road, Dorset Road, and Cornwall Road. Tomorrow the top course will be completed on Dover Road, Kent Road, and Windsor Road.

  • Friday, July 17 - Today the top course was completed on Dover Road, Kent Road, and York Road. Windsor Road was also partially completed. On Monday, Windsor Road, Dorset Road, and Cornwall Road will all be completed.

  • Monday, July 20 - Dorset Road, Cornwall Road and Windsor Road were completed today.  South Street, Stanley Street, Stanley Court and Konstin Place will be worked on tomorrow. 

  • Tuesday, July 21 - Paving stopped early today due to the rain. The first course was placed on South Street and partially on Stanley Street. Tomorrow the first course will be placed on Stanley Street, Stanley Court, and Konstin Place. Ellis Street will be worked on as well.

  • Wednesday, July 22 - Today the first course was placed on Konstin Place and Stanley Court. Stanley street was also worked on. Tomorrow, paving will begin with the top course at 3am on South Street. Stanley Street and Ellis street will also be worked on.

  • Friday, July 24 - Today the top course was placed on Ellis Street from the Route 9 on/off ramp to Stanley Street and from East Street to Rocky Hill Avenue. The top course was also placed on Stanley Court and the first course was completed on Stanley Street. On Monday the top course will be placed on Konstin Place and Stanley Street.

  • Monday, July 27 - Today the top course was completed on Konstin Place and Stanley Street. Tomorrow the top course will be completed on Ellis Street from Stanley Street to East Street.

  • Tuesday, July 28 - Today the top course was completed Ellis Street.

    This completes the 2026 Milling and Paving Program. Pavement Markings will be laid out and installed over the next month.